Project work packages: The project is split into activities (work packages) with well-defined deliverables, inputs and outputs. The duration of project is 18 months. Below the activities and associated milestones defined by deliverable (D) are described.



 PROJECT: EARTH OBSERVATIONS FOR BALTIC AND ARCTIC SHIPPING EO4BAS                                                                                                         WP 1

WP Title: Collection of geoinformation requirements and associated constraints
Company: DNV, Høvik, Norway with the collaboration of CGI and e-Geos, Rome, Italy
WP Manager: Janne Valkonen

Start Event: Project kick-off Meeting (06.03.2023)     Planned Date: T0 = Week 6
End Event: Delivery of D.1.2: Geoinformation Requirements Report                                                              Planned Date: T0+3months

Inputs:
•         Project proposal
•         The project management plan as agreed at KO.

Tasks:
•         Carry out desktop review of geoinformation requirements for the proposed activities. This shall include:
•         Descriptions of geoinformation requirements addressing key business processes of the industry sector where geoinformation play a role, considering:
           o    Differences due to the geographic regions and seasonality.
           o    Any requirements generated from generic issues like Health and Safety, Sustainable Development and legal and regulatory issues.

•         Establish a working area on the EARSC portal to facilitate the review of requirements with relevant actors from the concerned industry
•         Participate in a workshop with the industry sector and record/consolidate its outcome, in coordination with ESA and the key stakeholders engaged.

Outputs:

•         D1.1: Workshop 1 Report
•         D1.2: Geoinformation Requirements Report.